New Wave Communications has an extensive background in providing telecom solutions to some of the most distinguished customers in the world. Our team of specialists are dedicated to upholding the most rigid standards and delivering your project on time.
Structured Cabling Projects
Chesapeake College – Wye Mills MD
2014-2015: Provided complete network for new wing which consisted of four phases:
LAN cabling installation, switches and integration with existing campus network.
Wireless AP installation and integration to existing campus environment.
CATV cabling installation, splitters, taps and integration.
CCTV installation and integration to existing ONSSI software.
Windstream Corporation – MD, DC and VA
2008 to present: Provide field support and services to this leading service provider’s over 200,000
local businesses. Generated Income (past 5 years): $1.5 million
Marriott Corporation
July 2010 to present: Awarded several projects over the past three years for some of this company’s largest local hotels.
Marriott-Mayflower – Washington, DC
April 2012: Re-wired all existing guest rooms to an upgraded wireless solution. Provided Cat6 wiring for new front desk and restaurant renovations. Provided fiber backbone cabling between multiple closets.
Marriott Renaissance Hotel – Washington, DC
March 2013: Provided Cat5 wiring to multiple office locations throughout hotel.
Marriott-Wardman Park – Washington, DC
2010-2012: Provided Cat5 wiring for over 250 Wireless Access Points throughout hotel. Wired over 1300 guest rooms with Cat5 voice/data cabling. Installed fiber and copper backbone cabling between closets. Generated Income: $500,000
Marriott Metro Center – Washington, DC
January 2013: Provided Cat5 wiring for new Wireless Access Points throughout hotel. Provided fiber backbone cabling between multiple closets.
Marriott Westfields – Virginia
February 2013: Installed approximately 350 feet of armored 12 strand mm fiber from 1st floor main Telco/server room to 1st floor AV room.
American Career Institute – Silver Spring, MD
2012: Designed and implemented Cat5 and Cat6 cables for client. Contract Amount: $40,000
Arlington Public Schools Office – Arlington, VA
September 12, 20012 to January 13, 2013: Awarded contract through Sigal Construction for installation of Cat6 cabling to over 1300 locations. Installed CATV to over 100 locations. Designed speaker system with over 75 speakers and call buttons. Designed Telco closet with ladder racks, relay racks and fiber back bone. Contract Amount: $180,000
Remax – Columbia, MD
March 13, 2013 to April 13, 2013: Awarded contract by owner for the installation of Cat5 wiring to over 150 locations. Completed design build out of Telco closet and installation of speaker system. Contract Amount: $25,000
Norris Ford/Acura – Baltimore, MD
April 2013: Cut out asphalt parking lot to install approximately 300 feet of 4” rigid conduit for use of Verizon fiber.
Armed Forces Reserve Center Bristol, PA
Description – Over 2,000 feet of Wire Mesh Cable Tray and over 1,300 Cat 6 inside premise wire installations for a new military training facility. We were tasked with building 5 new telecomm rooms with 12 data racks, wire management, patch panels and power strips. We also installed new outside plant cabling to network the site’s 4 buildings using outdoor rated copper and fiber cable.
Schedule – 10 Months
Special Distinction – LEED PROJECT
NOAA Relocation Project at Dulles Airport Sterling, VA
Description – Over 1,200 feet of Wire Mesh Cable Tray, and over 60,000 ft. of Cat 6 inside premise wire installations for a new construction weather observation building. Project also included building a new telecom room with data racks, wire management, patch panels, power strips and grounding hardware. We also installed new outside plant cabling to network the site’s relocated multiple buildings and test beds using over 1 Mile of outdoor rated copper and fiber cable. We also integrated the site’s 2 card reader and video gate systems using fiber optic cabling and a media converter – fiber to coax – to activate the security gate system.
Schedule – 12 Months
Special Distinction – LEED PROJECT
Ft. McHenry National Park Baltimore, MD
Description – Supplied and installed over 3,000 feet of 100-pair outside plant copper cable and over 3,000 feet of 12- and 24-strand multi-mode fiber optic cable to network the existing administration building and Fort with the new Visitor Center. Supplied and installed outside plant protection blocks with terminations, supplied all ST fiber optic connectors and tipped all new fiber strands, labeled and tested all new cabling.
Schedule – 2 Months
Mary Ellen Henderson Middle School Falls Church, VA Description – Supplied and installed Cat 5e plenum copper wire for over 600 voice, data and CATV cable runs, including inside premise IDF to workstation wiring, backbone cabling to network the 4 floors for voice, data and CATV. Also supplied and installed voice, data and CATV outside plant cabling to network the new middle school back to the existing high school next door. Also supplied and installed new Cat 5e wiring in the existing high school as a change order to our base contract for the middle school new construction project.
Schedule – 12 Months